Milestone Achievement in Underground Operations
Trigon Metals achieved an average of 980 tonnes per day from underground operation over 30 consecutive days, 13 months ahead of schedule, fulfilling a key agreement with Sprott and significantly derisking operations.
High Copper Recovery Rate
Processed 77,300 tonnes with a copper recovery of 92.1% during the quarter, indicating efficient extraction processes.
Strategic Focus on High-Grade Underground Ore
Shift from open pit mining to high-grade underground ore is yielding positive results by improving overall copper grade and enhancing profitability.
Potential Capital Injection from Asset Sale
Trigon Metals is planning to sell the Kombat Mine, which could raise between USD 30 million to USD 50 million, allowing the company to focus on opportunities in Morocco and the Kalahari project.