Venture Global (VG) announced that it has notified its long-term customers that its Calcasieu Pass facility will commence commercial operations on April 15, 2025. The facility will achieve its commercial operation date, or COD, in under 68 months from its August 2019 final investment decision, despite substantial impacts including two hurricanes, the COVID-19 pandemic, and major unforeseen manufacturing issues, such as with the Heat Recovery Steam Generators forming part of the facility’s power island.