Endeavour Silver (EXK) announced the fabrication and installation of its primary ball mill trunnion at the Guanacevi mine. Guanacevi processing resumed to full capacity this week after the trunnion failure in August. After a 15-week period of operating at a reduced capacity averaging 620 tons per day, the newly fabricated trunnion was installed on November 30 with alignment testing occurring over the ensuing two weeks, restoring the plant to its designed capacity of 1,200 tpd. The total cost of fabrication and installation was just over $400K.