Jadestone Energy Inc (GB:JSE) has released an update.
Jadestone Energy has reported progress on its Akatara gas development project in Indonesia, with gas sales commencing and production increasing to reach a current rate of 11-14 mmscfd. The company is working on commissioning the AGPF’s export compressors to meet the daily contract quantity of 20 mmscfd. CEO Paul Blakeley expressed confidence in achieving full operational capacity once the compressors are fully commissioned.